EXAM C_S4PM_2504
80 questions (3 hrs)
69% cut score
Available in EN
Validate your SAP skills and expertise
This certification verifies that you possess the ability to perform an SAP project manager role. Project manager oversee the implementation of SAP solutions using the SAP Activate methodology, leverage SAP Cloud ALM for project management and monitoring, and facilitate Organizational Change Management to ensure smooth adoption and user acceptance throughout the project lifecycle.
Stay certified and stay ahead
Continuous learning and keeping your skills up to date is a priority and SAP Certification makes it easy for you to maintain your SAP skills and valid credentials.
The standard validity of your certification is 12 months.
Every time you successfully complete an assessment, the validity period is extended by 12 more months.
You’ll receive personalized communication to ensure that you don’t miss your certification expiry date.
Topic areas
Please see below the list of topics that may be covered within this SAP Certification and the courses that touches on these topics. Its accuracy does not constitute a legitimate claim. SAP reserves the right to update the exam content (topics, items, weighting) at any time.
SAP S/4HANA Cloud Public Edition Implementation
Exam percentage: 31-40%
Project Management / Organizational Change Management (OCM)
Exam percentage: 31-40%
SAP Activate methodology
Exam percentage: 31-40%
Examkingdom SAP C_S4PM_2504 Exam pdf

Best SAP C_S4PM_2504 Downloads, SAP C_S4PM_2504 Dumps at Certkingdom.com
Sample Question and Answers
QUESTION 1
Which type of testing should be done after a release upgrade has occurred?
A. Regression tests
B. User Acceptance tests
C. String tests
D. Integration tests
Answer: A
QUESTION 2
What are some characteristics of the SAP SHANA Migration Cockpit? Note: There are 2 correct answers to this question.
A. Combining the local and remote schema approaches into one migration project
B. Extensibility using the Legacy System Migration Workbench
C. Guidance and simulation of the migration process
D. Mapping source values to SAP SHANA target values
Answer: C,D
QUESTION 3
In the SAP Activate prepare phase, the cloud project is set up and officially launched.
Which change management activities are usually started in this phase?
Note: There are 3 correct answers to this question.
A. Identify the key stakeholders and conduct a stakeholder analysis
B. Conduct a detailed change impact analysis
C. Develop an initial change plan for the cloud project
D. Develop and align the change network strategy
E. Facilitate the role mapping process
Answer: A,C,D
QUESTION 4
Which SAP products relate to the scenarios included in the SAP Activate roadmap for the Intelligent Enterprise? Note: There are 3 correct answers to this question.
A. SAP Integrated Business Planning for Supply Chain
B. SAP SHANA Cloud
C. SAP Sales Cloud
D. SAP Concur
E. SAP Fieldglass
Answer: A,B,C
QUESTION 5
Which of the following configuration items CANNOT be changed after the initial provisioning of SAP SHANA Cloud Public Edition?
Note: There are 2 correct answers to this question.
A. Group currency
B. Custom fields in standard objects
C. User access rights
D. Fiscal Year Variant
Answer: A,D